How Mercedes-Benz turned research into reality

By Mustafa Bayülgen | Supply Chain QuarterlyQuarter 2 2012 issue

By adopting proven practices from the supply chain literature, a Mercedes-Benz bus factory in Turkey avoided “reinventing the supply chain wheel” while making big gains in production and efficiency.

As the year 2008 came to a close, the global economy was struggling. Even so, we at the Mercedes-Benz bus plant where I work in Hosdere, near Istanbul, Turkey, were determined that we would not simply weather the economic downturn but would also increase production capacity by 30 percent. We knew it would be a huge challenge because of economic conditions and the increasingly complex nature of supply chains. Nevertheless, we went ahead with the project, which ultimately proved successful.

Thanks to the efforts of a logistics task-force team that Mercedes-Benz Türk A.Ş. (MBT) formed to tackle that challenge, the plant was able to meet its goal. The team achieved success by aligning all logistics operations with production operations through a project called “Hosdere 2010—New Logistics Concept.” This project applied a concept that can best be described as “evidence-based supply chain practice” (EBSCP).

Simply put, EBSCP is the incorporation of proven practical or research findings into daily supply chain management practices. It involves taking what has already been discovered—examining best-practice examples and current research—and then implementing it and enhancing it in actual practice. This concept facilitates both everyday operational decisions and long-term strategic plans.

By drawing on established knowledge, EBSCP lets supply chain managers succeed in today’s challenging business environment, and it prevents mistakes stemming from inexperience or individual preferences. Critical to its success is employing people with appropriate skills and knowledge.

EBSCP allows supply chain managers to avoid the kind of “crash tests” companies often undergo when implementing new initiatives in complex, intertwined supply chains. Rather than innovate without guidance, they can take advantage of widely available information. For example, they can learn from journal articles and books published by supply chain researchers around the world who are rigorously working to establish principles and find solutions for problems. They can also learn from practitioners who share their experiences through case studies in journals and business publications, as well as through other means, such as professional associations and professional networking sites on the Internet.

In short, with so many complex challenges facing supply chain practitioners today, it makes sense to learn from and take advantage of already published, tested information and solutions to problems. By doing so, companies will strengthen their supply chains, and that will eventually lead to greater profitability and an improved quality of life around the world as products and services arrive where and when needed.

 

The logistics team begins its work

Mercedes-Benz Türk A.Ş. was founded in 1967 under the name Otomarsan A.Ş. in Istanbul, Turkey, by Daimler-Benz AG and its Turkish partners, Mengerler T. A.Ş. and Has Otomotiv A.Ş. The company’s initial production in Hosdere was 0.6 buses per day. By 1970, it was already exporting buses, mostly to the Middle East and North Africa. In 1986, the company added a truck production plant to its portfolio, in Aksaray, Turkey, and changed its name to Mercedes-Benz Türk A.Ş. in 1990.

Over the years, MBT, now a subsidiary of Daimler AG, evolved into a manufacturer of complete buses and trucks. An increase in export activities led MBT in 1995 to add a second bus plant in Hosdere and to convert the first plant to manufacture bus chassis and bodies for the new facility. A few years later, the new plant was expanded to include chassis and body operations, and the original plant was shut down. Today the Hosdere factory produces four basic bus models: Travego, Tourismo, Intouro, and Conecto. It has a production capacity of 14 buses per day, and it exports vehicles to Europe, Asia, and Africa. MBT also markets and sells Mercedes-Benz automobiles and light commercial vehicles in Turkey.

In 2008, in order to boost efficiency and to get the bus plant ready for a potential capacity increase, project “Hosdere 2010″ was launched. The first thing the management decided to do was to bring highly qualified and talented individuals together to form a logistics project team. (For more about the human resources considerations involved in EBSCP, see the sidebar “Invest in talent to make EBSCP a success.”)

The logistics team found that the plant was facing such problems as material shortages, excessive inventory, and high transportation costs. Previous attempts to solve them had not been entirely successful, and sometimes the outcomes of those attempts were not what managers had expected. Clearly more information was needed. Recognizing that practitioners and researchers around the world have confronted similar issues, the team decided to adopt an “evidence-based” approach, making use of published research findings to help it address those problems.

Since then, Mercedes-Benz Türk A.Ş. has implemented several supply chain practices that the logistics team developed while consulting research findings, case studies, and other published best practices. (The notes throughout this article refer to the published information sources that provided some of the ideas we incorporated into our solutions.) The following are just two examples of how we applied evidence-based supply chain practices to achieve significant cost and efficiency improvements that we might not have been able to achieve otherwise.

1. Matching material flow with production
One area where the logistics team applied EBSCP was in adapting the assembly parts warehouse and in-plant material-flow operations to the increased rate of production. As part of that effort, the team set out to devise a new process in the warehouse, since the existing process limited how quickly the warehouse could perform such tasks as picking, sorting, kitting, staging, and delivery to the assembly line. An associated problem was that the on-time availability of components at the assembly line was 99.38 percent. Although this might seem good at first glance, it’s actually on the poor side for an assembly plant and has considerable cost implications.

The team began by brainstorming several ideas, looking for ways to increase not only throughput but also parts availability and overall efficiency. The questions then were, which of the ideas would work, and what would be the best way to implement them? To answer those questions, the members consulted some books, articles, and other documents, and then combined that information with their past experiences and the theoretical knowledge provided by their formal educations. Using all of those resources, the team developed the following solution.

Approximately 20,000 components and raw materials were being stored in the warehouse. But only 0.5 percent of those items were delivered just-in-time to the assembly line after having been picked from a dedicated storage zone. For the rest, a pull system was used, where assembly workers issued internal orders in the MRP (materials resource planning) system in batches (usually in full pallets); warehouse workers picked those materials from their storage locations and then delivered them to the line. This practice resulted in a significant amount of inventory positioned in the assembly area but provided little protection from stock-outs.

The master production schedule was fixed for three days out. The logistics team hypothesized that if the data in the MRP system was 100-percent correct, then it was theoretically possible to pick materials in single pieces from the warehouse, sort them in the right order, place them on trolleys in kits, and deliver them to the corresponding assembly station just-in-time and in perfect synch with the three-day, fixed master production schedule. This would greatly reduce, if not eliminate altogether, the inventory of components located next to the production line. The strategy would also provide more space for production-related activities and reduce the non-value-added time that production workers spent walking back and forth between assembly stations and material storage locations, some of which were not optimally positioned. In addition, since almost all of the inventory would be in the warehouse area at any given time, it would be much easier to anticipate a probable stock-out a few days in advance just by looking at the current stock level in the warehouse and in-transit from the supplier. If there should be a high probability of a stock-out for a critical assembly item used in, say, the Conecto bus model, then the scheduled assembly date for Conecto buses could be pushed back a few days before it entered the three-day “frozen” zone, and other bus models for which materials were available could be brought forward.

Taking the above arguments into consideration, the team decided to increase the number of parts picked from the dedicated just-in-time zone in the warehouse. This basically meant that the team would have to balance the trade-off between the cost of adding some more warehouse space and the benefits of improved speed of delivery to the line. Since this proposed system would allow for almost no margin of error in the MRP data, critical parameters entered into the MRP system, such as pallet capacities, batch sizes, and delivery frequencies, were carefully checked and corrected when necessary.

After implementing this plan, the percentage of materials picked from the dedicated zone and delivered just-in-time to the assembly line increased from 0.5 percent to nearly 15 percent. Because we learned from our reading that a reduction in the time to pick and deliver was a direct function of warehouse configuration,4 we made some modifications to the configuration of the warehouse that helped to increase picking and delivery speed. Another renovation was the conversion of the small-parts storage area to an automated storage and retrieval (AS/RS) system.

2. Supply base localization
As we approached the year 2008, MBT became interested in acquiring more parts from local Turkish suppliers. In 2008 we established a group within our logistics department that was assigned to deal with localization of supplies. One of our aims was to decrease the company’s total costs by reducing logistics-related costs. (Our thinking was similar to the total-cost-of-ownership approach described in the article “Time to come home?” in CSCMP’s Supply Chain Quarterly.5) Over the last four years, the division has successfully localized more than 5 percent of the components that originally had been imported from suppliers located outside Turkey.

Using more local suppliers was also a way to perform risk management by addressing both supply side risks and catastrophic risks, two of the five main risk categories outlined in an article on that subject by Stephan and Bode (2008).6 We also put forward a hypothesis that we needed to balance both prevention programs and response preparedness in our risk management practices.7 Proof that this hypothesis was correct came a couple of years later, when many firms that were stronger in prevention programs had difficult times during such disruptions as the massive earthquake and tsunami in Japan and the eruption of the Eyjafjallajökull volcano in Iceland. No manager would have thought to include such unusual, extreme events in a prevention program or to develop contingency plans for them.8

Meanwhile, many companies that were stronger in response preparedness continued spending time, effort, and money on response activities due to the disruptions, even though at least some of those efforts could have been avoidable if they had paid more attention to prevention. It should also be noted that the volcano eruption and the earthquake led managers around the world to realize that diversifying their supplier base might be beneficial. However, managers should not have needed those supply chain disruptions to come to that realization, since the principle that diversifying the supplier base by splitting orders among multiple suppliers could indeed be beneficial (depending on certain factors) was already widely evidenced in literature.9, 10 As discussed in those articles, the expected reduction in shortage costs could make order-splitting worthwhile for some very critical components.

With those thoughts in mind, we decided to perform cost-benefit analyses for new components. If risks were high, then we would source the components dually, from one foreign and one local supplier. This would diversify the supply base in terms of both alternative suppliers and geographical locations.

Thanks to our decision to implement the dual or multiple sourcing strategy wherever possible, we avoided supply disruptions during such events as the eruption of the Icelandic volcano and the earthquake and tsunami in Japan. We also had some experiences closer to home. For example, in 2011 a very trusted local supplier of ours had a fire that incapacitated its plant for more than a month. Despite that disruption we kept the material flowing in, with one portion coming from the foreign supplier and the other portion from another local supplier. And in January 2012 we faced another potential disruption when a foreign supplier of a critical assembly part was unable to deliver it because of the extreme winter conditions in Europe. Trucks could not move, railways were covered with ice, ships couldn’t leave ports due to extremely high winds, and rivers flooded very near the Turkish border. We were able to manage despite those weather conditions because we had already split the order between a local and a foreign supplier. The local supplier, located just two hours away from our plant, sent its quota of parts just-in-time, and that quantity was enough to keep production going until the shipment from the other supplier arrived. Looking back at those situations, it is clear that the costs we would have incurred if we had experienced disruptions would have far outweighed the costs associated with placing orders with the second, local supplier.

 

Proof positive

Thanks to the two implementations above, as well as to many others that are outside of the scope of this article, MBT saw a steep rise in efficiency indicators. As shown in Figure 1, the on-time-delivery service level of parts to the assembly line rose from 99.38 percent in 2008 to 99.81 percent in 2011. Although this 0.43-percent increase may seem like a small nuance, it actually represents a significant cost reduction. That’s because when parts are available where and when needed, there is less overtime work and no penalties for late deliveries of buses to customers. As of February 2012, the on-time rate had reached 99.85 percent.

[Figure 1] Service level of deliveries from warehouse to assembly
Figure 1 – Service level of deliveries from warehouse to assembly

The drop in raw material and component inventories is also a strong indicator of how EBSCP has contributed to the cost savings Mercedes Benz Türk A.Ş. has achieved so far. Figure 2 compares each year’s average raw material and component inventory levels with that of 2008. We are aiming to continue the trendline shown in the chart in the coming years.

[Figure 2] Raw material and component inventories held as a percentage of the 2008 level per each bus produced
Figure 2 – Raw material and component inventories held as a percentage of the 2008 level per each bus
  produced

 

Figure 3 shows late deliveries of buses as a percentage of the daily production rate, from the assembly line to the respective sales organizations that deliver the buses to the end customers. The abrupt fall from the year 2008 to 2009 was mostly attributable to the impact of the economic crisis. During that time we had more production capacity then demand, which meant we could deliver buses with more ease than in a normal year. As the demand gradually increased in 2010, the backlog also increased as expected in 2010 through 2011. The rate of the backlog increase in 2011 was less than that of 2010 because the effects of the EBSCP implementations had started to kick in. We have recently begun to see the full impact of the implementations, as demonstrated by a backlog of just 0.29 percent as of February 2012—despite a record-high demand and daily production rate.

 

[Figure 3] Average daily backlog as a percentage of annual sales

Enlarge image

 Figure 3 – Average daily backlog as a percentage of annual sales  

As a result of the implementations described above and other Hosdere 2010 projects, MBT has achieved a significant drop in costs and has sustained profitability despite the global economic downturn. This success has attracted the attention of upper-level management at Daimler AG. As a result, the bus plant has hosted several visits and received recognition from the parent company’s management. In fact, Daimler AG’s top-level management meeting was held in Turkey in July 2011, and during the event executives had a chance to see the implementations’ results firsthand.

Top management has been so impressed with our accomplishments that it is considering implementing some of our ideas elsewhere in the company. For example, an extension of the just-in-time delivery to the line strategy, better known by the German term Spezialgutabwicklung (or the Turkish term set sevkiyat among MBT employees), is now being considered for incorporation into an ongoing process-harmonization initiative for other bus plants in Europe. The lean in-plant logistics system we developed is about to become a companywide benchmark and, with minor local variations, has the potential to be implemented in any of Daimler’s bus plants.

We believe it is important to share our knowledge and ideas with others. Accordingly, our plant has hosted visits by many logistics- and manufacturing-related groups and logistics specialists from all over Europe, as well as by faculty and students from local universities.

The MBT logistics team can point to many achievements. Yet even while we work on current projects, the fast-changing nature of business means that already there are new challenges that must be addressed. As we deal with them, the evidence-based supply chain practices concept that has proven so successful in the past will continue to be our guide.

Invest in talent to make EBSCP a success

Getting the full benefit from evidence-based supply chain practices (EBSCP) takes more than simply reading academic and other literature, or sharing information with peers. It also requires having the right people on staff—supply chain and logistics professionals who have the knowledge, skills, and abilities that are necessary to understand, develop, and carry out complex ideas.

The supply chain discipline calls for quick decision making. This allows supply chains to become lean and agile. When employees have to get approval from their superiors for every little deviation from the norm, the company loses flexibility. By employing the right supply chain talent, managers will not have to think twice before delegating responsibility to subordinates who have the skills to make the best decisions. Furthermore, companies need individuals who are proficient in converting intangible supply chain concepts to tangible cost and profit figures. That way they can induce the right supply chain alignment for the organization by speaking the chief executive officer’s language, eventually leading to lower total costs and higher profitability.The logistics team members who made the implementations described in this article and many others possible for Mercedes-Benz Türk A.Ş. (MBT) were selected from among the company’s existing employees. Since MBT had done a good job of attracting, continuously educating, and encouraging talent as well as of providing individuals with the necessary tools, management did not have to look elsewhere for team members.

At MBT, we have found that the following talent-centered principles laid the groundwork for establishing EBSCP and getting the greatest benefits from what we learn. Here are recommendations based on our experience:

1. Attract talented people with relevant educational backgrounds. Imagine asking a very talented and well-educated engineer to perform brain surgery on a patient. As odd as it may sound, this is analogous to assigning an individual with an irrelevant educational background to perform a supply chain-related task. Academics at times complain about the conceptual difficulties that many managers in the field have with statistical reasoning11 and say that this hinders practitioners’ ability to use models to solve problems. A lack of ability by managers and front-line personnel to understand and apply analytical models is a factor that stands in the way of good decisions.12 Therefore, it makes sense to pick supply chain team members who have relevant educational backgrounds. The right formal education provides individuals with the necessary skills, tools, methodological knowledge, and statistical reasoning ability. Furthermore, it has been shown that supply chain education and training increases supply resiliency.13

A well-planned, formal education with a strong technical component provides individuals with the knowledge of the most up-to-date optimization methods. For example, plenty of mathematical optimization methods exist in the supply chain literature. Many of them are fairly easy to implement on spreadsheets and offer strong support for supply chain managers’ decision making. However, failure to attract people with the right technical knowledge means that these optimization methods may not be fully put into practice, which means lost opportunities for the supply chain organization.

It should also be noted that today’s competitive environment requires that supply chain professionals not only be experts in their own field but also have an idea about what’s happening elsewhere. A sound supply chain education, preferably supplemented with a background in another discipline, such as engineering, finance, accounting, marketing, and so forth, will enrich the field. Since attracting and retaining talent is not an easy task, supply chain executives should not fail to consider retention incentives to keep talent in the profession. The fast-paced and challenging—not to mention exciting and fulfilling—nature of the supply chain profession should be marketed among younger generations to attract them to the discipline.

2. Provide opportunities for continuous learning. Due to the ever-changing nature of the discipline, it is of utmost importance for supply chain professionals to be dedicated learners.14 In addition to formal education, regular exposure to what is happening in the supply chain field through attending events such as conferences, seminars, and workshops (both within and outside of their industry) is a must.

Supply chain managers also must work with their subordinates in order to prepare annual education plans for them and collaborate with universities to ensure continuous education opportunities for their employees. Managers can, in turn, cooperate with academics to co-instruct undergraduate and/or graduate courses as a way to help develop new talent for the supply chain field. (Thanks to collaborative efforts and activities between MBT and several local universities, for example, the author of this article had the privilege of serving as a co-instructor for an undergraduate course at a local college.)

3. Encourage team members to conduct research and contribute ideas. When they encounter complicated situations, supply chain executives must make the most of their team’s knowledge by eliciting subordinates’ ideas and making them a part of the decision process. Encouraging them to provide evidence for their ideas will directly lead them to evaluate research findings and best-practice examples.

4. Provide team members with the necessary tools. It is intuitive that even the best talent cannot achieve top-level performance without up-to-date decision-support tools. It is the supply chain executives’ responsibility to make sure that individuals have access to the right tools, such as appropriate software. This should be a high priority.

Notes:
1. Marcia MacLeod, “Making the Warehouse Visible,” Automotive Logistics, July-September (2011).
2. A. E. Ellinger, M. Natarajarathiram, G. A. Frank, J. B. Gray, D. Hofman, and K. O’Marah, “Supply Chain Management Competency and Firm Financial Success,” Journal of Business Logistics 32.3 (2011): 214-226.
3. C. Eroglu and C. Hofer, “Inventory Types and Firm Performance: Vector Autoregressive and Vector Error Correction Models,” Journal of Business Logistics 32.3 (2011): 227-239.
4. G. Ghiani, G. Laporte, and R. Musmanno, Introduction to Logistics Systems Planning and Control, John Wiley & Sons (2004).
5. Harry Moser, “Time to Come Home?,” CSCMP’s Supply Chain Quarterly, Q4 (2011).
6. M. W. Stephan and C. Bode, “An Empirical Examination of Supply Chain Performance Along Several Dimensions of Risk,” Journal of Business Logistics 29.1 (2008): 307-325.
7. Bruce Arntzen, “Global Supply Chain Risk Management Part 1: Differences in Attitudes,” Massachusetts Institute of Technology Center for Transportation and Logistics White Paper (2010).
8. James A. Cooke, “Supply Chain versus the Volcano,” CSCMP’s Supply Chain Quarterly Q2 (2010).
9. D. J. Thomas and J. E. Tyworth, “Pooling Lead-Time Risk by Order Splitting: A Critical Review,” Transportation Research Part E 42.4 (2006): 245-257.
10. P. D. Berger, A. Gerstenfeld, and A. Z. Zeng, “How many suppliers are best? A decision analysis approach,” The International Journal of Management Science 32.1 (2004): 9-15.
11. E. A. Silver, D. F. Pyke, and R. Peterson, Inventory Management and Production Planning and Scheduling, John Wiley & Sons (1998): 50.
12. Thomas H. Davenport and Jerry O’Dwyer, “Tap into the Power of Analytics,” CSCMP’s Supply Chain Quarterly Q4 (2011).
13. J. Blackhurst, K. S. Dunn, and C. W. Craighead. “An Empirically Derived Framework of Global Supply Resiliency,” **italic{Journal of Business Logistics} 32.4 (2011): 374-391.
14. Tim M. Stratman, “Why You Should Never “Graduate’, “ CSCMP’s Supply Chain Quarterly Q4 (2011).